Inadequate Interoperability: A Closer Look at the Costs

Published

Author(s)

Robert E. Chapman

Abstract

The 2004 NIST interoperability cost study estimated an annual cost burden of $15.8 billion due to inadequate interoperability in the capital facilities segment of the U.S. construction industry. The $15.8 billion estimate is the sum of individual annual cost burdens for four key stakeholder groups: architects and engineers ($1.2 billion); general contractors ($1.8 billion); specialty fabricators and suppliers ($2.2 billion); and owners and operators ($10.6 billion). From a business perspective, these costs represent approximately one percent of annual receipts for each of the first three stakeholders and nearly three percent of the annual value of construction put in place for owners and operators. Building on the NIST interoperability cost study, this paper addresses the cost burden and business-related issues by explaining the methodology behind the estimates, analyzing key cost impacts, and discussing challenges and implications for change within the industry.
Proceedings Title
ISARC 2005| 22nd
Conference Dates
September 11-14, 2005
Conference Location
Ferrara, IT
Conference Title
International Symposium on Automation and Robotics in Construction

Keywords

Capital facilities, commercial buildings, cost analysis, economic impact evaluation, industrial facilities, integration and automation technologies, interoperability

Citation

Chapman, R. (2005), Inadequate Interoperability: A Closer Look at the Costs, ISARC 2005| 22nd, Ferrara, IT (Accessed March 28, 2024)
Created September 1, 2005, Updated February 19, 2017